Expansion of mooring facilities and realisation of new jetty

Challenge

Design & Construction of mooring facilities and new jetty.

Our solution

 

  • New jetty consisting of prefab concrete piles (#500), prefab concrete beams/plates and in situ top layer

  • Realisation of 9 dolphins Ø1820 for mooring facilities for seagoing vessels

  • Realisation of 88 m, fender wall and 3 dolphins Ø1220 for mooring facilities for inland vessels/coasters

  • Realisation 11 dolphins Ø1220 for mooring facilities for crane pontoon 

  • Dredging works of 200,000 m3 with depths ranging from – 8.15 m NAP to –17.50 m NAP 